PSC (psc.gov.np) website is currently down, so new notices and results cannot be fetched right now. We will update as soon as it is back.

लोक सेवा आयोगको वेबसाइट अहिले चलेको छैन। आयोग सञ्चालनमा आउनासाथ सूचना तथा नतिजा अपडेट गरिनेछ।

These questions mix formulas with reasoning. The fastest candidates choose the correct model before calculating: cost-selling, work-rate, distance-speed-time, odd days or sufficiency.

Core Definitions

Data sufficiency

Standard definition: A question type where you decide whether given statements provide enough information to answer, without necessarily solving fully.

Exam meaning: पूरै solve नगरी statement पर्याप्त छ कि छैन भनेर निर्णय गर्ने question।

Work rate

Standard definition: Amount of work completed per unit time.

Exam meaning: एक unit time मा सकिने कामको भाग।

How To Think

Treat profit as price relation, work as rate addition, speed as distance/time, and calendar as odd-day counting. Data sufficiency requires independence testing of each statement.

Commercial and Rate Formulas

Know the formula and what each variable means.

Topic Formula Meaning
Profit SP – CP Selling price minus cost price
Loss CP – SP Cost price minus selling price
Simple interest P*T*R/100 Principal-time-rate
Work Rate = 1/time Combine rates
Speed Distance/time Unit consistency

Calendar and Sufficiency

Calendar problems use remainders; sufficiency uses logical completeness.

  • Odd days are remainder days after complete weeks.
  • Leap year has 366 days and 2 odd days; ordinary year has 1 odd day.
  • Century leap rules need divisibility by 400.
  • In data sufficiency, test statement I alone, II alone, then together.
  • Do not solve more than needed.

Formulas and Rules

  • Profit % = profit / CP x 100.
  • Loss % = loss / CP x 100.
  • Simple interest = PRT/100.
  • If A finishes work in x days, A rate = 1/x per day.
  • Distance = speed x time.
  • Ordinary year odd days = 1; leap year odd days = 2.

Step-by-Step Method

  • Identify variable and formula family.
  • Check units before calculation.
  • For work, convert days into rates.
  • For calendar, count odd days and take mod 7.
  • For data sufficiency, avoid using outside assumptions.

Worked Examples

  • CP=100, SP=120 gives profit 20 and profit percent 20%.
  • A does work in 10 days and B in 15 days. Combined rate = 1/10 + 1/15 = 1/6, so together 6 days.
  • In sufficiency, if statement I gives exact age and II only gives relation, I alone may be sufficient.
Area Shortcut Trap
Profit-loss Percent on CP Using SP as base
Work Add rates Adding days
Speed Normalize units Mixing km/h and m/s
Calendar Use odd days Forgetting leap year
Sufficiency Test alone first Solving with both too early

Exam Point

  • Profit/loss percentage is based on cost price.
  • In work questions, never add times directly.
  • Calendar answer depends on remainder after division by 7.
  • Data sufficiency is about enough information, not final numeric answer.

Visual Practice

  • Create CP-SP-profit triangle.
  • Draw work-rate table.
  • Make odd-day calendar chart.
  • Use data sufficiency decision tree.

Common Mistakes

  • Adding work days instead of rates.
  • Ignoring unit conversion.
  • Misapplying leap year rule.
  • Combining statements before testing separately.

MCQ Revision

  • Profit percent base?
  • A 10-day worker rate?
  • Leap year odd days?
  • Simple interest formula?
  • What does data sufficiency ask?

Final Summary

  • Formula choice matters more than long calculation.
  • Rate models solve work and speed.
  • Calendar uses odd-day modular logic.
  • Sufficiency tests information completeness.